Start release cycle checklist documentation

This is a start to capturing the activities that need to happen during a
typical release cycle to help us track tasks and avoid missing important
steps.

Change-Id: I137694a460cbefe499231270faa0d1d2e1a11066
Signed-off-by: Sean McGinnis <sean.mcginnis@gmail.com>
This commit is contained in:
Sean McGinnis 2019-04-19 09:31:58 -05:00
parent ad45320e81
commit b96470467b
No known key found for this signature in database
GPG Key ID: CE7EE4BFAF8D70C8
2 changed files with 164 additions and 1 deletions

View File

@ -26,7 +26,7 @@ APIs.
Programming HowTos and Tutorials Programming HowTos and Tutorials
-------------------------------- --------------------------------
.. toctree:: .. toctree::
:maxdepth: 3 :maxdepth: 2
development.environment development.environment
testing testing
@ -43,6 +43,13 @@ Programming HowTos and Tutorials
rolling.upgrades rolling.upgrades
groups groups
Managing the Development Cycle
------------------------------
.. toctree::
:maxdepth: 1
releasecycle
Documentation Contribution Documentation Contribution
-------------------------- --------------------------
.. toctree:: .. toctree::

View File

@ -0,0 +1,156 @@
===================
Release Cycle Tasks
===================
This document describes the relative ordering and rough timeline for
all of the steps related to tasks that need to be completed during a
release cycle for Cinder.
Before PTG (after closing previous release)
===========================================
#. Collect topics and prepare notes for PTG discussions in an etherpad.
Add a link to the etherpad to the list of PTG etherpads (for example:
https://wiki.openstack.org/wiki/PTG/Train/Etherpads)
Between Summit and Milestone-1
==============================
#. Review output from the PTG and set Review-Priority on any high
priority items identified from those discussions. Send out recap to
the mailing list.
#. Add any Cinder-specific schedule information to the release calendar
(https://review.openstack.org/#/c/509019/)
#. Focus on spec reviews to get them approved and updated early in
the cycle to allow enough time for implementation.
#. Review new driver submissions and give early feedback so there isn't
a rush at the new driver deadline. Check for status of third party CI
and any missing steps they need to know about.
#. Review community-wide goals and decide a plan or response to
them.
Milestone-1
===========
#. Propose library releases for os-brick or python-cinderclient if there
are merged commits ready to be released. Watch for any releases
proposed by the release team.
#. Check progress on new drivers and specs and warn contributors if
it looks like they are at risk for making it in this cycle.
Between Milestone-1 and Milestone-2
===================================
#. Review stable backports and release status.
#. Watch for and respond to updates to new driver patches.
Milestone-2
===========
#. Propose library releases for os-brick or python-cinderclient if there
are merged commits ready to be released. Watch for any releases
proposed by the release team.
Between Milestone-2 and Milestone-3
===================================
#. Review stable backports and release status.
#. Set Review-Priority for any os-brick changes that are needed for
feature work to make sure they are ready by the library freeze prior
to Milestone-3.
#. Make sure any new feature work that needs client changes are proposed
and on track to land before the client library freeze at Milestone-3. Ensure
microversion bumps are reflected in cinderclient/api_versions.py
MAX_VERSION.
#. The week before Milestone-3, propose releases for unreleased changes
in os-brick. Include branch request for stable/$series creation.
Milestone-3
===========
#. Propose releases for unreleased changes in python-cinderclient and
python-brick-cinderclient-ext. Watch for releases proposed by the
release team. Include branch request for stable/$series creation.
#. Set Review-Priority -1 for any feature work not complete in time for
inclusion in this cycle. Remind contributors that FFE will need to be
requested to still allow it in this cycle.
#. Prepare "prelude" release notes as
summaries of the content of the release so that those are merged
before their first release candidate.
#. Complete the responses to community-wide goals if not already done.
#. Start assembling cycle-highlights for the team.
Between Milestone-3 and RC1
===========================
#. Add cycle-highlights in the releases deliverable file.
RC1 week
========
#. Propose RC1 release for cinder or watch for proposal from the release team.
Include stable/$series branching request with the release.
#. Finalize any cycle-highlights for the release cycle.
#. Remind contributors that ``master`` is now the next cycle but focus should
be on wrapping up the current cycle.
#. Watch for translation and new stable branch patches and merge them quickly.
Between RC1 and Final
=====================
#. Propose additional RC releases as needed.
.. note::
Try to avoid creating more than 3 release candidates so we are not
creating candidates that consumers are then trained to ignore. Each
release candidate should be kept for at least 1 day, so if there is a
proposal to create RCx but clearly a reason to create another one,
delay RCX to include the additional patches.
#. Watch for translation patches and merge them quickly.
#. Make sure final RC request is done one week before the final release date.
#. Watch for the final release proposal from the release team to review and +1
so team approval is included in the metadata that goes onto the signed tag.
Final Release
=============
#. Start planning for next release cycle.
#. Check for bugfixes that would be good to backport to older stable branches.
#. Propose any bugfix releases for things that did not make the freeze for
final library or service releases.
Post-Final Release
==================
#. Make sure at least three SQLAlchemy-Migrate migrations are reserved
for potential backports (https://review.openstack.org/#/c/649436/).
#. Unblock any new driver submission patches that missed the previous
release cycle's deadline.
#. Review approved cinder-specs that were merged to the previous cycle
folder that did not get implemented. Revert or move those specs to the
next cycles's folder.